July 2020 Progress Photos

July 2020 Progress Photos

Work continues on both the exterior and interior of the building. The exterior is being bricked in and insulated. Duct work, ceilings and sheet rock are being placed inside. Windows are being installed with hopes of entirely sealing in the building soon. Progress is...
March 2020 Progress Photos

March 2020 Progress Photos

Milestone: Tower Crane Removed Continue work on: Electrical Rough-in, Completing framing, Fire Protection, and Brick. Click through slideshow below. Orientation: 1 Photos provided by R. C. Mathews from their monthly report give you a close up view of the...
January 2020 Progress Photos

January 2020 Progress Photos

Milestone: Cast-In Place Concrete Topped Out by the end of the Month with approximately 4500 Cubic Yards of Concrete Poured for the Project to date. For Reference: 1 Cubic Yard = ~4050 LBS 4050LBS x 4500 CY = 18,225,000 LBS of concrete for this job A Space Shuttle...
December Progress Photos

December Progress Photos

Most work was done on the third level, completing the layout and rough in of electrical and plumbing for 3A. Click through slideshow below. Photos provided by R. C. Mathews from their monthly report give you a close up view of the...
November Progress Photos

November Progress Photos

95% of the Excavation was completed. Structural steel began to be placed. Orientation: 1 Photos provided by R. C. Mathews from their monthly report give you a close up view of the...

October Progress Photos

Photos provided by R. C. Mathews from their monthly report give you a close up view of the progress.